To connect the proposed wind project to the grid, Piikani Resource Development Ltd. plans to construct a new
substation, named Piikani 1149S Substation.

To accommodate the project, AltaLink is proposing to:

  • construct approximately 10 km of new 138 kilovolt (kV) transmission line along
    one of two potential routes from PRDL’s proposed Piikani 1149S Substation to
    AltaLink’s existing Windy Flats 138S Substation
  • install two new 138 kV circuit breakers and associated equipment at the Windy
    Flats 138S Substation
  • install optical grounding wire (OPGW) between PRDL’s proposed Piikani 1149S
    Substation and AltaLink’s existing Windy Flats 138S Substation