BowArk Drywood Gas Generation Connection

This project involves building approximately 150 metres of new 138 kV (kilovolt) transmission line (called 164BL) to connect BowArk’s proposed Harland Substation to AltaLink’s existing 164L transmission line.

 

 


Project Status:
application

Anticipated Project Schedule

October 2019 Start Construction
January 2020 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.