Pegasus Lake Substation, located in Woodlands County, approximately 18 kilometres north of the City of Whitecourt in NW-35-61-12-W5.
The proposed upgrades include:
• replacing one existing 69/25 kilovolt (kV) transformer with one new 72/26.5 transformer and associated equipment
• replacing one existing 69 kV circuit breaker and associated equipment
• minor substation equipment upgrades
- August 2023
- Notice of application filing and project approval
- May 2023
- Project newsletter
- Detail photo map
Project Status:
construction
Anticipated Project Schedule
August 2023 | Start Construction |
August 2024 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.