Tempest Wind Power Connection Project

To connect its project to the grid, TransAlta is constructing a new 138 kilovolt (kV) transmission line, located approximately 20 kilometres south of the Town of Taber. To accommodate the connection, AltaLink’s proposed project includes:

• modifying the existing 172EL transmission line at one of two potential locations
• installing a new underground fibre optic cable between one of two potential connection points and an existing substation in the area (called Suncor Hillridge), located in NW-36-8-18-W4M
• installing a new telecommunications tower at TransAlta’s Tempest Substation, located in SE-19-7-17-W4M


Project Status:
consultation

Anticipated Project Schedule

January 2025 Start Construction
April 2025 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.