To connect its project to the grid, TransAlta is constructing a new 138 kilovolt (kV) transmission line, located approximately 20 kilometres south of the Town of Taber. To accommodate the connection, AltaLink’s proposed project includes:
• modifying the existing 172EL transmission line at one of two potential locations
• installing a new underground fibre optic cable between one of two potential connection points and an existing substation in the area (called Suncor Hillridge), located in NW-36-8-18-W4M
• installing a new telecommunications tower at TransAlta’s Tempest Substation, located in SE-19-7-17-W4M
Project Status:
consultation
Anticipated Project Schedule
January 2025 | Start Construction |
April 2025 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

