To connect the TC Energy Berland River Project to the grid, AltaLink is proposing changes to its transmission system in the area.
AltaLink’s proposed project is located approximately 25 kilometres (km) south of the Town of Fox Creek.
AltaLink’s proposed project includes:
• building a new substation
• building approximately 55-60 km of new 138 kilovolt (kV) transmission line
• building a new 138 kV switching station
• installing new telecommunications equipment
Project Status:
consultation
Anticipated Project Schedule
January 2025 | Start Construction |
December 2025 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

