Nova Solar Power Connection

RES is constructing a new substation and transmission line as part of their new solar power facility located in Wheatland County, approximately four kilometres southwest of Carseland. RES is considering two connection points for their transmission line. To connect RES’s new solar power facility to the grid, AltaLink is proposing to modify the existing 924L/927L transmission line at one of two potential locations, depending on the final connection point.


Project Status:
hold

Anticipated Project Schedule

Fall 2022 Start Construction
Spring 2023 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

Subscribe to Updates

Back to Project Map Back to Project Listing

©2023 AltaLink