Solar Krafte Vauxhall Connection

Solar Krafte Utilities Inc. (Solar Krafte) has requested a connection to the transmission system for their proposed Vauxhall Solar Farm. To facilitate this connection AltaLink is proposing to construct a transmission line, operated and maintained by AltaLink, to connect Solar Krafte’s proposed substation and solar farm to the electric system.


Project Status:
application

Anticipated Project Schedule

Spring 2024 Start Construction
Summer 2024 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

Subscribe to Updates

Back to Project Map Back to Project Listing

©2023 AltaLink