AltaLink's existing 164L and 616L transmission lines were both constructed more than 60 years ago and portions of both lines are located in a high-risk fire area. We are proposing to rebuild portions of these lines to ensure that a safe and reliable supply of power is available for years to come.
- May 2023
- Project update letter
- Detailed photo map
- Strip maps
- October 2021
- Project newsletter
- Detail photo map
- Strip maps
- COVID-19 Letter
Project Status:
consultation
Anticipated Project Schedule
Fall 2024 | Start Construction |
Winter 2024 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

