AltaLink's existing 150L transmission line was constructed in 1956. We are proposing to rebuild a portion of this line to ensure that a safe and reliable supply of power is available in the area for years to come.
- August 2022
- Notice of application filing
- June 2022
- Project update letter
- Detail photo map
- December 2021
- Project update newsletter
- Detail photo map
- Strip map
- October 2020
- Project update newsletter
- Detail photo map
- Strip map
- COVID-19 project letter
- May 2020
- 150L Newsletter
- DP Map
- Strip Maps
Project Status:
application
Anticipated Project Schedule
Fall 2024 | Start Construction |
Spring 2025 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

